The electricity crisis has become more severe across the country with the start of the new year.

Transmission systems were reportedly affected due to a technical fault at Guddu power plant and reduction in hydro power generation. Unannounced power outages in all power distribution companies (DISCOs), including LESCO, has made life difficult for people.

The transmission system was affected by reduced power generation and heavy fog in the plains.

RELATED STORIES

Unannounced load shedding continues every hour in various areas of the LESCO region. Due to an increase in shortfall, the duration of load shedding in the city exceeded 12 hours.

According to an INP from Kushmore, the breaker could not be repaired despite the passage of several hours after fire broke out in the switchyard of Guddu Thermal Power Plant following a technical fault. Sources claim that it may take 15 days to buy a new breaker.

On the other hand, Powerhouse officials have said the alternate high transmission line also tripped due to heavy fog.

Electricity supply to different areas of Sindh, Punjab and Balochistan remained suspended for more than five hours due to tripping of the alternative high transmission line. According to Guddu Thermal Power House officials, it is difficult to restore power from the alternate high transmission line until the sun comes out.

Lack of electric supply for more than six hours has put a halt on businesses as well as shopkeepers, factory workers.